Construction and Improvements on EWC Campus this Fall
President Claudette H. Williams, Ed.D. announced the progress of numerous construction and improvement projects on EWC’s campus. After completing assessments and reviewing bids from contractors, President Williams and her administration are moving forward with plans to address over 20-years of deferred maintenance on EWC’s campus, utilizing the generous $1 million donation from Mr. and Mrs. Michael Ward. After obtaining the Board of Trustees’ approval, the following construction and improvement activities will take place during the fall semester.
In addition to the construction projects, EWC’s band will receive new uniforms; broken instruments will be replaced; and there will be upgrades and equipment repairs for the athletics’ weight room. These additional blessings were possible by exercising due diligence in utilizing the funds awarded by Mr. and Mrs. Ward.
We must ALL be part of this movement to take EWC from good to great! <Back to Home>
President Claudette H. Williams, Ed.D. announced the progress of numerous construction and improvement projects on EWC’s campus. After completing assessments and reviewing bids from contractors, President Williams and her administration are moving forward with plans to address over 20-years of deferred maintenance on EWC’s campus, utilizing the generous $1 million donation from Mr. and Mrs. Michael Ward. After obtaining the Board of Trustees’ approval, the following construction and improvement activities will take place during the fall semester. | Project | Timeline |
| Roof Repair (2008) | |
| Hatcher/Stewart | July – August |
| Tookes | July – August |
| Student Union | July – September |
| Morris Cone A | July – September |
| Morris Cone B | July – September |
| Salter Hall | July – September |
| Centennial | August – September |
| Upstairs Gymnasium Build-Out | July – December |
| Hatcher Stewart | |
| Elevator Repair | July – August |
| Lab Renovation | August – September |
| Air Condition System Repairs | |
| Morris Cone A | July – August |
| Salter Hall | July – August |
| Tookes | July – August |
| Receiving | July – August |
| Other Repairs | |
| Telephone System | July – August |
| Cafeteria Renovation | July – January 2009 |
| Weight Room Upgrades | July – August |
In addition to the construction projects, EWC’s band will receive new uniforms; broken instruments will be replaced; and there will be upgrades and equipment repairs for the athletics’ weight room. These additional blessings were possible by exercising due diligence in utilizing the funds awarded by Mr. and Mrs. Ward.